Title: Sobrecustos e atrasos de megaprojetos de energia: quando maior é pior
Author(s)/Inventor(s): Callegari, Camila Ludovique
Advisor: Szklo, Alexandre Salem
Co-advisor: Schaeffer, Roberto
Abstract: O sucesso do sistema energético esteve historicamente associado à percepção que megaprojetos, projeto cujo investimento é superior a um bilhão de dólares, produzem economias de escala. Os planejadores acreditavam que os sistemas deveriam ser composto por poucas, porém grandes, unidades de fornecimentos e distribuição. Diante desse cenário, o objetivo deste trabalho foi realizar uma avaliação do desempenho dos indicadores de custo e tempo de entrega da construção dos megaprojetos de energia. Ao desenvolver esta analise buscou-se contribuir com a melhoria dos processos de planejamento e implantação de novos empreendimentos energéticos. Para realizar a avaliação utilizou-se uma base de dados internacional com todos os tipos de plantas de geração de energia elétrica. Obtiveram-se as curvas de distribuição de probabilidade de resultado de custo e tempo de entrega para todas as fontes, bem como uma avaliação da influência geográfica e do tamanho do projeto nas variáveis sobrecusto e atraso. Fez-se também uma análise qualitativa dos sobrecustos e atrasos em megaprojetos e uma revisão bibliográfica acerca das principais questões atreladas à tomada de decisão e fundamentos da gestão de megaprojetos. Por fim, utilizaram-se as funções de distribuição de probabilidade estimadas para avaliar o desempenho das mega hidrelétricas construídas recentemente no país e indicou-se o nível de risco de sobrecusto e atraso a que os projetos do setor estão sujeitos.
Abstract: Energy system success has historically been associated with the perception that megaprojects, projects whose investment exceeds one billion dollars, produce economies of scale. Planners use to believe that systems should be composed of a few, but large, units of supply and distribution. In view of this scenario, the objective of this work was to carry out an evaluation of the performance of cost and delivery time construction indicators of energy megaprojects. In developing this analysis, it sought to contribute to the improvement of the planning and implementation processes of new energy projects. To carry out the evaluation, an international database was used with all types of electric power generation plants. It were obtained the results of cost overruns and delays probability distribution curves for all the sources, as well as an evaluation of geographical and size influence of the project on the variables cost and delay. A qualitative analysis was made of the cost overruns and delays in megaprojects and a bibliographical review about the main issues linked to the decision making and foundations of megaproject management. Finally, it were used the probability distribution functions to evaluate the performance of mega hydroelectric plants recently built in the country and it were indicated the risk level of cost overruns and delay that the projects of the sector are subject.
Keywords: Planejamento energético
Sobrecustos e atrasos
Estimativa probabilística
Subject CNPq: CNPQ::ENGENHARIAS::ENGENHARIA DE PRODUCAO
Program: Programa de Pós-graduação em Planejamento Energético
Production unit: Instituto Alberto Luiz Coimbra de Pós-Graduação e Pesquisa de Engenharia
Publisher: Universidade Federal do Rio de Janeiro
Issue Date: Feb-2017
Publisher country: Brasil
Language: por
Right access: Acesso Aberto
Appears in Collections:Planejamento Energético

Files in This Item:
File Description SizeFormat 
876219.pdf2.17 MBAdobe PDFView/Open


Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.